Ralph Izzo

Chief executive: Public Service Enterprise Group (before 2014 to 1 Sep 2022)

34commitments announced
27with a clear outcome
27met on time
100%on-time rate

Commitments are credited to the chief executive in office on the day they were announced. Where a deadline fell after the leader left, the entry is marked. Sources for each leadership change: Public Service Enterprise Group filing.

Commitments announced under Ralph Izzo

Public Service Enterprise Groupannounced 2 Nov 2021 Submit the Infrastructure Advancement Program filing to regulators No record found31 Dec 2021
Public Service Enterprise Groupannounced 2 Nov 2021 Submit an Infrastructure Advancement Program filing with the New Jersey Board of Public Utilities No record found31 Dec 2021
Public Service Enterprise Groupannounced 26 Feb 2021 Make PSEG Power's fleet coal-free No record found30 Jun 2021
Public Service Enterprise Groupannounced 26 Feb 2021 Achieve a 2023 methane reduction goal of about 22% from 2018 levels due after leader left Met31 Dec 2023
Public Service Enterprise Groupannounced 4 Dec 2020 Close the acquisition of a 25% interest in the Ocean Wind project Met30 Jun 2021
Public Service Enterprise Groupannounced 23 Nov 2020 Begin the marketing process for the remaining non-nuclear generating fleet of PSEG Power Met31 Dec 2020
Public Service Enterprise Groupannounced 31 Jul 2020 Become coal-free through the planned early retirement of Bridgeport 3 Met30 Jun 2021
Public Service Enterprise Groupannounced 26 Feb 2020 Issue the first Climate Report using science-based targets and TCFD reporting framework No record found30 Apr 2020
Public Service Enterprise Groupannounced 31 Oct 2019 Eliminate coal from PSEG Power's fuel mix Met30 Jun 2021
Public Service Enterprise Groupannounced 31 Oct 2019 Complete exit of coal units from PSEG Power's generation fleet Met30 Jun 2021
Public Service Enterprise Groupannounced 30 Jul 2019 Submit the Energy Strong II settlement stipulation to the NJBPU for approval Met30 Sep 2019
Public Service Enterprise Groupannounced 29 May 2019 Complete the Bridgeport Harbor 5 CCGT and add it to ISO-NE Met30 Jun 2019
Public Service Enterprise Groupannounced 27 Feb 2019 Retire the 383 MW Bridgeport Harbor coal-fired generating station Met30 Jun 2021
Public Service Enterprise Groupannounced 30 Oct 2018 File Zero Emission Certificate application for three New Jersey nuclear units No record found31 Dec 2018
Public Service Enterprise Groupannounced 30 Oct 2018 Complete the Bridgeport Harbor 5 combined-cycle gas turbine unit Met30 Jun 2019
Public Service Enterprise Groupannounced 30 Oct 2018 Complete the Bridgeport Harbor 5 CCGT construction program Met30 Jun 2019
Public Service Enterprise Groupannounced 1 Aug 2018 Complete GSMP I and Energy Strong infrastructure programs No record found31 Dec 2018
Public Service Enterprise Groupannounced 1 Aug 2018 File the Clean Energy Future (CEF) program with the New Jersey BPU Met31 Dec 2018
Public Service Enterprise Groupannounced 1 Aug 2018 Complete Bridgeport Harbor 5 generation unit Met30 Jun 2019
Public Service Enterprise Groupannounced 1 Aug 2018 Achieve commercial start-up of the 485 MW Bridgeport Harbor gas-fired CCGT Met30 Jun 2019
Public Service Enterprise Groupannounced 1 Aug 2018 Begin the GSMP II gas infrastructure replacement program Met31 Dec 2019
Public Service Enterprise Groupannounced 30 Apr 2018 Place Sewaren 7 in service Met30 Jun 2018
Public Service Enterprise Groupannounced 30 Apr 2018 Place Keys Energy Center in service Met30 Jun 2018
Public Service Enterprise Groupannounced 30 Apr 2018 Place Bridgeport Harbor 5 in service Met30 Jun 2019
Public Service Enterprise Groupannounced 23 Feb 2018 Place the Keys gas-fired combined-cycle plant in service Met30 Jun 2018
Public Service Enterprise Groupannounced 24 Feb 2017 Retire the Hudson and Mercer coal/gas-fired generating stations Met1 Jun 2017
Public Service Enterprise Groupannounced 24 Feb 2017 Begin commercial start-up of 1,300 MW of new gas-fired combined cycle capacity at Keys Energy Center and Sewaren Met30 Jun 2018
Public Service Enterprise Groupannounced 24 Feb 2017 Begin commercial start-up of 485 MW Bridgeport Harbor gas-fired combined cycle power plant Met30 Jun 2019
Public Service Enterprise Groupannounced 5 Oct 2016 Retire the Hudson and Mercer generation stations in New Jersey Met1 Jun 2017
Public Service Enterprise Groupannounced 16 May 2016 Develop an additional 100 MW dc of grid-connected solar capacity on landfills and brownfields No record found31 Dec 2021
Public Service Enterprise Groupannounced 2 May 2016 Add Keys, Sewaren 7 and Bridgeport Harbor generating units to Power's fleet Met31 Dec 2019
Public Service Enterprise Groupannounced 11 Mar 2016 Place the Keys and Sewaren combined cycle units into operation Met31 Dec 2018
Public Service Enterprise Groupannounced 11 Mar 2016 Place the Bridgeport 5 combined cycle unit into operation Met31 Dec 2019
Public Service Enterprise Groupannounced 19 Feb 2016 Bring the new 485-MW gas-fired combined cycle plant at Bridgeport Harbor Station into operation Met30 Jun 2019

Is this record wrong, or are you Ralph Izzo? Add a statement or ask for a correction.