| Public Service Enterprise Groupannounced 2 Nov 2021 |
Submit the Infrastructure Advancement Program filing to regulators |
No record found31 Dec 2021 |
| Public Service Enterprise Groupannounced 2 Nov 2021 |
Submit an Infrastructure Advancement Program filing with the New Jersey Board of Public Utilities |
No record found31 Dec 2021 |
| Public Service Enterprise Groupannounced 26 Feb 2021 |
Make PSEG Power's fleet coal-free |
No record found30 Jun 2021 |
| Public Service Enterprise Groupannounced 26 Feb 2021 |
Achieve a 2023 methane reduction goal of about 22% from 2018 levels due after leader left |
Met31 Dec 2023 |
| Public Service Enterprise Groupannounced 4 Dec 2020 |
Close the acquisition of a 25% interest in the Ocean Wind project |
Met30 Jun 2021 |
| Public Service Enterprise Groupannounced 23 Nov 2020 |
Begin the marketing process for the remaining non-nuclear generating fleet of PSEG Power |
Met31 Dec 2020 |
| Public Service Enterprise Groupannounced 31 Jul 2020 |
Become coal-free through the planned early retirement of Bridgeport 3 |
Met30 Jun 2021 |
| Public Service Enterprise Groupannounced 26 Feb 2020 |
Issue the first Climate Report using science-based targets and TCFD reporting framework |
No record found30 Apr 2020 |
| Public Service Enterprise Groupannounced 31 Oct 2019 |
Eliminate coal from PSEG Power's fuel mix |
Met30 Jun 2021 |
| Public Service Enterprise Groupannounced 31 Oct 2019 |
Complete exit of coal units from PSEG Power's generation fleet |
Met30 Jun 2021 |
| Public Service Enterprise Groupannounced 30 Jul 2019 |
Submit the Energy Strong II settlement stipulation to the NJBPU for approval |
Met30 Sep 2019 |
| Public Service Enterprise Groupannounced 29 May 2019 |
Complete the Bridgeport Harbor 5 CCGT and add it to ISO-NE |
Met30 Jun 2019 |
| Public Service Enterprise Groupannounced 27 Feb 2019 |
Retire the 383 MW Bridgeport Harbor coal-fired generating station |
Met30 Jun 2021 |
| Public Service Enterprise Groupannounced 30 Oct 2018 |
File Zero Emission Certificate application for three New Jersey nuclear units |
No record found31 Dec 2018 |
| Public Service Enterprise Groupannounced 30 Oct 2018 |
Complete the Bridgeport Harbor 5 combined-cycle gas turbine unit |
Met30 Jun 2019 |
| Public Service Enterprise Groupannounced 30 Oct 2018 |
Complete the Bridgeport Harbor 5 CCGT construction program |
Met30 Jun 2019 |
| Public Service Enterprise Groupannounced 1 Aug 2018 |
Complete GSMP I and Energy Strong infrastructure programs |
No record found31 Dec 2018 |
| Public Service Enterprise Groupannounced 1 Aug 2018 |
File the Clean Energy Future (CEF) program with the New Jersey BPU |
Met31 Dec 2018 |
| Public Service Enterprise Groupannounced 1 Aug 2018 |
Complete Bridgeport Harbor 5 generation unit |
Met30 Jun 2019 |
| Public Service Enterprise Groupannounced 1 Aug 2018 |
Achieve commercial start-up of the 485 MW Bridgeport Harbor gas-fired CCGT |
Met30 Jun 2019 |
| Public Service Enterprise Groupannounced 1 Aug 2018 |
Begin the GSMP II gas infrastructure replacement program |
Met31 Dec 2019 |
| Public Service Enterprise Groupannounced 30 Apr 2018 |
Place Sewaren 7 in service |
Met30 Jun 2018 |
| Public Service Enterprise Groupannounced 30 Apr 2018 |
Place Keys Energy Center in service |
Met30 Jun 2018 |
| Public Service Enterprise Groupannounced 30 Apr 2018 |
Place Bridgeport Harbor 5 in service |
Met30 Jun 2019 |
| Public Service Enterprise Groupannounced 23 Feb 2018 |
Place the Keys gas-fired combined-cycle plant in service |
Met30 Jun 2018 |
| Public Service Enterprise Groupannounced 24 Feb 2017 |
Retire the Hudson and Mercer coal/gas-fired generating stations |
Met1 Jun 2017 |
| Public Service Enterprise Groupannounced 24 Feb 2017 |
Begin commercial start-up of 1,300 MW of new gas-fired combined cycle capacity at Keys Energy Center and Sewaren |
Met30 Jun 2018 |
| Public Service Enterprise Groupannounced 24 Feb 2017 |
Begin commercial start-up of 485 MW Bridgeport Harbor gas-fired combined cycle power plant |
Met30 Jun 2019 |
| Public Service Enterprise Groupannounced 5 Oct 2016 |
Retire the Hudson and Mercer generation stations in New Jersey |
Met1 Jun 2017 |
| Public Service Enterprise Groupannounced 16 May 2016 |
Develop an additional 100 MW dc of grid-connected solar capacity on landfills and brownfields |
No record found31 Dec 2021 |
| Public Service Enterprise Groupannounced 2 May 2016 |
Add Keys, Sewaren 7 and Bridgeport Harbor generating units to Power's fleet |
Met31 Dec 2019 |
| Public Service Enterprise Groupannounced 11 Mar 2016 |
Place the Keys and Sewaren combined cycle units into operation |
Met31 Dec 2018 |
| Public Service Enterprise Groupannounced 11 Mar 2016 |
Place the Bridgeport 5 combined cycle unit into operation |
Met31 Dec 2019 |
| Public Service Enterprise Groupannounced 19 Feb 2016 |
Bring the new 485-MW gas-fired combined cycle plant at Bridgeport Harbor Station into operation |
Met30 Jun 2019 |