KeptBase · the outside view

How often are promises like this kept?

Before a company announces a date, or an investor relies on one, the best first question is not “do we believe them?” but “how often does this kind of promise land on time?” KeptBase answers it from 7,068 checked corporate outcomes since 2016.

Look up a base rate

– delivered on time

And when they are late, how late?

37 daysmedian delay past the deadline
93 daysone in four late commitments slipped at least this long
199 daysone in ten slipped at least this long
71%of all 7,068 checked commitments were on time

Same build snapshot as the quality page. The count here is smaller than “clear outcomes” there because KeptBase uses only S&P 500 members whose commitment has a known type and horizon, and only met, late and not-met outcomes. Rates are confirmed and unconfirmed outcomes together; small cells carry wide uncertainty and are left blank below 20.

Delays measured on 882 commitments that were delivered late, from the deadline the company set to the date delivery was shown.

The full table

On-time rate by kind of commitment and horizon, any listed company. Cells with fewer than 20 outcomes are left blank rather than guessed.

Kind of commitmentUnder 6 months6 to 12 monthsOver 12 months
Deal or transaction closing82% (1561)77% (519)72% (144)
Product launch or release75% (774)68% (397)53% (242)
Regulatory filing or approval step75% (236)64% (102)53% (36)
Project milestone67% (994)67% (622)64% (347)
New facility, plant or site70% (462)65% (345)56% (287)

Who uses the outside view

Companies, before announcing

If promises like yours land on time less than six times in ten, announce a wider window or a firmer plan. A date you keep builds credibility; a date you miss costs it, and can invite claims.

Investors, before relying

Start from the base rate, then adjust for what you know about the company. An 18-month approval step is a very different bet from a 3-month deal closing.

Lenders and project teams, before scheduling

Use the delay figures as a buffer: if one late project in four slips four months or more, a contingency of one month is not a plan.

Preliminary, October 2026. Most outcomes are machine-checked (measured outcome accuracy 89%); figures are recalculated with every site update and restated after each audit. Aggregate only: no company is named or scored here. Not investment advice. Method: Methodology.

Check a draft announcement

Send us the dated commitments in a draft release, and we will return the base rate and delay range for each, privately.