Public Service Enterprise Group
Retire the 383 MW Bridgeport Harbor coal-fired generating station
Delivered by the deadline
AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.
- Announced
- 27 Feb 2019
- Due
- 30 Jun 2021
- Delivered
- 31 May 2021
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“the mid-2021 retirement of the 383 MW Bridgeport Harbor coal-fired generating station”
What we found
Evidence strength A What the grades mean
The 10-K states Bridgeport Harbor 3 coal plant was retired effective May 31, 2021, before the mid-2021 deadline; the August 2021 8-K corroborates the early retirement.
-
A Public Service Enterprise Group 10-K filed 2022-02-24
“Effective May 31, 2021, PSEG Power retired its Bridgeport Harbor 3 coal plant.” ✓ confirmed on the page
-
A Public Service Enterprise Group 8-K filed 2021-08-03
“PSEG Power eliminated all coal from its generation mix with the early retirement of Bridgeport Harbor Station Unit 3.” ✓ confirmed on the page
Market reaction: the shares moved -1.5% against the S&P 500 over the three sessions around the disclosure (23 Feb 2022 to 28 Feb 2022). What this measures
Checked 16 Oct 2026.
Commitment lineage
Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.
- Scope drift 0.0%
- Language weakened: firm → expected
- 3 versions
-
Version 1 · original · stated 27 Feb 2019
Deadline 30 Jun 2021 (“mid-2021”) · target 383 MW
-
Version 2 · stated 30 Jul 2019
Deadline 30 Jun 2021 (“mid-2021”) · wording firm
“eliminating all coal by mid-2021, when the Bridgeport Harbor 3 coal-fired generating plant is scheduled to be retired”
-
Version 3 · stated 26 Feb 2020
Deadline 30 Jun 2021 (“in June 2021”) · target 383 MW · wording expected
“the planned retirement of 383 MW of coal-fired generation at Bridgeport Harbor 3 in June 2021”
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Facility other
- Indicative materiality
- Medium rules
- Action
- Retire
- Deliverable
- 383 MW Bridgeport Harbor coal-fired generating station retirement
- Target
- 383 MW
- Where
- Connecticut
- In the company’s control
- High
- Specificity
- Medium
How this entry was checked
- Commitment recordedThe company's words were matched word for word against the filing.
- First checkAn AI model, Claude (Anthropic), read the company's later filings and recorded the outcome with a quoted passage.
- Second check: agreesA different AI model, Gemini (Google), re-read the evidence without being told the outcome and reached the same answer.
Confirmed. This outcome counts towards the company's Kept Score. How verification works
Are you Public Service Enterprise Group? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2019-PEG-011506 · Corrections policy