KeptIndex

Public Service Enterprise Group

Retire the 383 MW Bridgeport Harbor coal-fired generating station

Delivered by the deadline

AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.

Announced
27 Feb 2019
Due
30 Jun 2021
Delivered
31 May 2021
  • Deadline
  • Met
  • Late
  • Not met
  • Today

What the company said

“the mid-2021 retirement of the 383 MW Bridgeport Harbor coal-fired generating station”

What we found

Evidence strength A What the grades mean

The 10-K states Bridgeport Harbor 3 coal plant was retired effective May 31, 2021, before the mid-2021 deadline; the August 2021 8-K corroborates the early retirement.

  • A
    Public Service Enterprise Group 10-K filed 2022-02-24 Regulatory filing · published 24 Feb 2022 · retrieved 16 Oct 2026 · kept permanently by the SEC · fingerprint a309b2f309fa
    “Effective May 31, 2021, PSEG Power retired its Bridgeport Harbor 3 coal plant.” ✓ confirmed on the page
  • A
    Public Service Enterprise Group 8-K filed 2021-08-03 Regulatory filing · published 3 Aug 2021 · retrieved 16 Oct 2026 · kept permanently by the SEC · fingerprint 18e6221f5f1a
    “PSEG Power eliminated all coal from its generation mix with the early retirement of Bridgeport Harbor Station Unit 3.” ✓ confirmed on the page

Market reaction: the shares moved -1.5% against the S&P 500 over the three sessions around the disclosure (23 Feb 2022 to 28 Feb 2022). What this measures

Checked 16 Oct 2026.

Commitment lineage

Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.

  • Scope drift 0.0%
  • Language weakened: firm → expected
  • 3 versions
  1. Version 1 · original · stated 27 Feb 2019

    Deadline 30 Jun 2021 (“mid-2021”) · target 383 MW

  2. Version 2 · stated 30 Jul 2019

    Deadline 30 Jun 2021 (“mid-2021”) · wording firm

    “eliminating all coal by mid-2021, when the Bridgeport Harbor 3 coal-fired generating plant is scheduled to be retired”

    Source for this version

  3. Version 3 · stated 26 Feb 2020

    Deadline 30 Jun 2021 (“in June 2021”) · target 383 MW · wording expected

    “the planned retirement of 383 MW of coal-fired generation at Bridgeport Harbor 3 in June 2021”

    Source for this version

Commitment DNA

The structured record of this commitment. Fields the company did not state are left blank rather than guessed.

Event type
Facility other
Indicative materiality
Medium rules
Action
Retire
Deliverable
383 MW Bridgeport Harbor coal-fired generating station retirement
Target
383 MW
Where
Connecticut
In the company’s control
High
Specificity
Medium

How this entry was checked

  1. Commitment recordedThe company's words were matched word for word against the filing.
  2. First checkAn AI model, Claude (Anthropic), read the company's later filings and recorded the outcome with a quoted passage.
  3. Second check: agreesA different AI model, Gemini (Google), re-read the evidence without being told the outcome and reached the same answer.

Confirmed. This outcome counts towards the company's Kept Score. How verification works

Are you Public Service Enterprise Group? You can publish an official statement next to this entry, free. Add a statement.

Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.

Report an error in this entry Reference: KI-C-2019-PEG-011506 · Corrections policy