| Marathon Petroleumannounced 5 May 2026 |
Complete the El Paso FCC upgrade |
Met30 Jun 2026 |
| Marathon Petroleumannounced 5 May 2026 |
Complete the Robinson jet project |
Being checked30 Sep 2026 |
| Marathon Petroleumannounced 5 May 2026 |
Complete the Titan Complex expansion |
Open31 Dec 2026 |
| Marathon Petroleumannounced 5 May 2026 |
Complete the Galveston Bay Distillate Hydrotreater |
Open31 Dec 2027 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the yield improvement project at the El Paso refinery |
Met30 Jun 2026 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Bay Runner pipeline |
Being checked30 Sep 2026 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Harmon Creek III gas processing plant |
Being checked30 Sep 2026 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Blackcomb pipeline |
Open31 Dec 2026 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the product export flexibility project at the Garyville refinery |
Open31 Dec 2027 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the feedstock optimization project at the Garyville refinery |
Open31 Dec 2027 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Traverse pipeline |
Open31 Dec 2027 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Marcellus Gathering System expansion |
Open30 Jun 2028 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Eiger Express pipeline |
Open30 Jun 2028 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the first Gulf Coast fractionation facility |
Open31 Dec 2028 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Gulf Coast LPG export terminal |
Open31 Dec 2028 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Secretariat II gas processing plant |
Open31 Dec 2028 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the Rio Bravo pipeline |
Open31 Dec 2029 |
| Marathon Petroleumannounced 3 Feb 2026 |
Complete the second Gulf Coast fractionation facility |
Open31 Dec 2029 |
| Marathon Petroleumannounced 4 Nov 2025 |
Bring Titan Complex sour gas treating plant online |
Open31 Dec 2026 |
| Marathon Petroleumannounced 4 Nov 2025 |
Complete BANGL pipeline expansion |
Open31 Dec 2026 |
| Marathon Petroleumannounced 4 Nov 2025 |
Bring Eiger Express natural gas pipeline into service |
Open30 Jun 2028 |
| Marathon Petroleumannounced 5 Aug 2025 |
Close the acquisition of Northwind Midstream |
Not met30 Sep 2025 |
| Marathon Petroleumannounced 5 Aug 2025 |
Bring Northwind Midstream sour gas treating capacity online |
Open31 Dec 2026 |
| Marathon Petroleumannounced 5 Aug 2025 |
Bring LPG export terminal into service |
Open31 Dec 2028 |
| Marathon Petroleumannounced 6 May 2025 |
Close acquisition of additional 5% stake in Matterhorn Express pipeline |
No record found30 Jun 2025 |
| Marathon Petroleumannounced 6 May 2025 |
Close acquisition of 55% interest in BANGL, LLC |
Met31 Jul 2025 |
| Marathon Petroleumannounced 6 May 2025 |
Complete Los Angeles refinery utility integration and modernization project |
Met31 Dec 2025 |
| Marathon Petroleumannounced 6 May 2025 |
Complete Robinson refinery jet fuel flexibility project |
Open31 Dec 2026 |
| Marathon Petroleumannounced 6 May 2025 |
Bring BANGL pipeline expansion online |
Open31 Dec 2026 |
| Marathon Petroleumannounced 6 May 2025 |
Bring Traverse Pipeline into service |
Open31 Dec 2027 |
| Marathon Petroleumannounced 6 May 2025 |
Bring Gulf Coast fractionation facilities into service |
Open31 Dec 2029 |
| Marathon Petroleum Corpannounced 4 Feb 2025 |
Bring Secretariat processing plant online in Permian basin |
Late31 Dec 2025 |
| Marathon Petroleum Corpannounced 4 Feb 2025 |
Bring Harmon Creek III processing plant and de-ethanizer online in Northeast |
Open31 Dec 2026 |
| Marathon Petroleum Corpannounced 4 Feb 2025 |
Bring Blackcomb and Rio Bravo pipelines online for Permian to Gulf Coast natural gas transport |
Open31 Dec 2026 |
| Marathon Petroleum Corpannounced 4 Feb 2025 |
Expand BANGL NGL pipeline from 250 thousand bpd to 300 thousand bpd capacity |
Open31 Dec 2026 |
| Marathon Petroleum Corpannounced 4 Feb 2025 |
Bring LPG export terminal and associated pipeline online with ONEOK partnership |
Open31 Dec 2028 |
| Marathon Petroleum Corpannounced 4 Feb 2025 |
Bring fractionation complex online at Galveston Bay with two 150 thousand bpd facilities |
Open31 Dec 2029 |
| Marathon Petroleumannounced 5 Nov 2024 |
Complete expansion of the BANGL pipeline to 250 thousand barrels per day |
No record found31 Mar 2025 |
| Marathon Petroleumannounced 5 Nov 2024 |
Bring the Blackcomb and Rio Bravo natural gas pipelines into service |
Open31 Dec 2026 |
| Marathon Petroleumannounced 5 Nov 2024 |
Reach 800 thousand barrels per day of fractionation capacity in the Northeast |
Open31 Dec 2026 |