Skip to content

Person-checked company records fromPerson-checked records $750See a worked exampleHuman review in progress

Talk to sales

KeptIndex

Executive Record

Mark D. Millett

Chief executive: Steel Dynamics Inc. (before 2014 to 1 Jan 2027)

31commitments announced
16with a clear outcome
8met on time
50%on-time rate

Commitments are credited to the chief executive in office on the day they were announced. Where a deadline fell after the leader left, the entry is marked. Sources for each leadership change: Steel Dynamics Inc. filing.

Commitments announced under Mark D. Millett

Steel Dynamics Inc.announced 20 Oct 2026 Ship finished automotive products from the first Continuous Annealing and Solution Heat line Open31 Dec 2026
Steel Dynamics Inc.announced 18 Sep 2026 Begin producing material for customer qualification on the second CASH line at the Columbus aluminum mill Open31 Dec 2026
Steel Dynamics Inc.announced 18 Sep 2026 Ship commercial material from the first CASH line at the Columbus aluminum mill Open31 Dec 2026
Steel Dynamicsannounced 21 Jul 2026 Transition the third cold mill to commercial operations Being checked31 Aug 2026
Steel Dynamicsannounced 21 Jul 2026 Commence automotive sales Open31 Dec 2026
Steel Dynamicsannounced 21 Jul 2026 Begin material qualifications for the second CASH line Open31 Dec 2026
Steel Dynamicsannounced 18 Jun 2026 Begin material qualification at the third cold mill Being checked31 Jul 2026
Steel Dynamicsannounced 21 Apr 2026 Commission the third cold mill at the Columbus, Mississippi aluminum facility Being checked30 Sep 2026
Steel Dynamicsannounced 21 Apr 2026 Commission the second continuous anneal and solution heat treat (CASH) line Being checked30 Sep 2026
Steel Dynamicsannounced 18 Jun 2025 Begin shipping aluminum flat rolled products from the Mississippi and Mexico facilities Met30 Jun 2025
Steel Dynamicsannounced 23 Apr 2025 Ship commercial aluminum flat rolled coils Met30 Jun 2025
Steel Dynamicsannounced 18 Mar 2025 Begin shipping material from the Columbus, Mississippi aluminum mill Met30 Jun 2025
Steel Dynamicsannounced 23 Jan 2025 Produce commercially viable products at the aluminum facility in Mississippi Not met30 Jun 2025
Steel Dynamicsannounced 24 Jan 2024 Begin operating the biocarbon production facility No record found31 Dec 2024
Steel Dynamicsannounced 19 Jul 2022 Begin operations at the satellite recycled aluminum slab center in Mexico Not met31 Dec 2024
Steel Dynamicsannounced 19 Jul 2022 Begin operations at the aluminum flat rolled mill Late31 Mar 2025
Steel Dynamicsannounced 21 Oct 2021 Start steel production at the Sinton Texas EAF Flat Roll Steel Mill Not met31 Dec 2021
Steel Dynamicsannounced 20 Apr 2021 Begin operating four additional value-added flat roll steel coating lines Not met31 Dec 2022
Steel Dynamicsannounced 19 Apr 2021 Begin production at the Sinton Steel Mill Late30 Sep 2021
Steel Dynamicsannounced 19 Apr 2021 Begin production at the new Southern U.S. coating lines Met31 Dec 2022
Steel Dynamicsannounced 28 Nov 2018 Begin construction of a new flat roll steel mill Met31 Dec 2020
Steel Dynamicsannounced 28 Nov 2018 Commence operations at the new flat roll steel mill Partly met31 Dec 2021
Steel Dynamicsannounced 22 Oct 2018 Achieve an annual run-rate of 800,000 to 900,000 tons at the Heartland facility No record found30 Jun 2019
Steel Dynamicsannounced 19 Sep 2018 Reopen the rolling mill in Ashland, Kentucky No record found30 Nov 2018
Steel Dynamicsannounced 25 Jul 2018 Increase Heartland steel production to 40,000 tons per month No record found31 Dec 2018
Steel Dynamicsannounced 25 Jul 2018 Reach an annual run-rate of 800,000 to 900,000 tons of flat roll steel No record found30 Jun 2019
Steel Dynamicsannounced 15 May 2018 Complete the acquisition of Heartland Met30 Sep 2018
Steel Dynamicsannounced 23 Oct 2017 Complete replacement and upgrade of two ladle furnace cranes at the Butler Flat Roll Division No record found31 Dec 2017
Steel Dynamicsannounced 23 Oct 2017 Complete upgrade of the hot strip mill at the Columbus Flat Roll Division Met31 Dec 2017
Steel Dynamicsannounced 10 Jul 2017 Complete the Structural and Rail Division expansion project Late31 Dec 2018
Steel Dynamicsannounced 6 Jul 2016 Complete the acquisition of Vulcan Threaded Products Met31 Aug 2016

Is this record wrong, or are you Mark D. Millett? Add a statement or ask for a correction.

The Deadline Report

One email a week: the corporate commitments that came due, which were met, which slipped, and what is due next. Free. Stop any time.

No advertising. We never sell or share your address.