| DTE Energyannounced 28 Jul 2026 | Complete 1,700 miles of pole top maintenance (PTMM) | Open31 Dec 2026 |
| DTE Energyannounced 28 Jul 2026 | Complete pole top maintenance on half of the system and 100% of pole top inspections | Open31 Dec 2029 |
| DTE Energyannounced 17 Feb 2026 | Place the 220 MW battery energy storage project in service | Open31 Dec 2026 |
| DTE Energyannounced 17 Feb 2026 | Convert Belle River unit 2 from coal to natural gas | Open31 Dec 2026 |
| DTE Energyannounced 30 Oct 2025 | Submit regulatory filing requesting approval of the data center power contract | Met31 Oct 2025 |