Gerard M. Anderson

Chief executive: DTE Energy Co. (before 2014 to 1 Jul 2019)

36commitments announced
6with a clear outcome
3met on time
–rate shown after 15 outcomes

Commitments are credited to the chief executive in office on the day they were announced. Where a deadline fell after the leader left, the entry is marked. Sources for each leadership change: DTE Energy Co. filing.

Commitments announced under Gerard M. Anderson

DTE Energyannounced 24 Apr 2019 Complete construction of the cogeneration project for Ford Motor Company due after leader left No record found31 Dec 2019
DTE Energyannounced 7 Feb 2019 File the Integrated Resource Plan with regulators No record found31 Mar 2019
DTE Energyannounced 7 Feb 2019 Make the Ford Motor cogeneration project operational due after leader left No record found31 Dec 2019
DTE Energyannounced 7 Feb 2019 Double renewable energy capacity due after leader left No record found31 Dec 2022
DTE Energyannounced 24 Oct 2018 Bring the Ford cogeneration project online due after leader left No record found31 Dec 2019
DTE Energyannounced 25 Jul 2018 Break ground on the new natural gas plant Met31 Aug 2018
DTE Energyannounced 25 Jul 2018 Complete the Bluestone expansion No record found30 Sep 2018
DTE Energyannounced 25 Jul 2018 Close one to two additional cogeneration or RNG deals No record found31 Dec 2018
DTE Energyannounced 25 Jul 2018 Place the Birdsboro project in service No record found31 Dec 2018
DTE Energyannounced 25 Jul 2018 Place the Eastern System Upgrade expansion in service No record found31 Dec 2018
DTE Energyannounced 4 May 2018 Bring the Bluestone and Millennium pipeline expansions in service No record found31 Dec 2018
DTE Energyannounced 16 Feb 2018 Break ground on the new wind park No record found30 Jun 2018
DTE Energyannounced 25 Oct 2017 Break ground on natural gas-fired power plant in Michigan due after leader left No record found31 Dec 2019
DTE Energyannounced 25 Oct 2017 Begin operations of the industrial energy services project due after leader left No record found31 Dec 2019
DTE Energyannounced 26 Jul 2017 Place the industrial central energy plant in service due after leader left No record found31 Dec 2019
DTE Energyannounced 23 Jun 2017 Make major infrastructure investments at 20-25 substations due after leader left No record found31 Dec 2021
DTE Energyannounced 9 Jun 2017 Impact 33% of electric circuits with infrastructure resilience upgrades due after leader left No record found31 Dec 2020
DTE Energyannounced 19 May 2017 Install 140 miles of gas main replacement No record found31 Dec 2017
DTE Energyannounced 19 May 2017 Reach 100% remote monitoring capability on DTE Electric system due after leader left No record found31 Dec 2019
DTE Energyannounced 26 Apr 2017 Achieve a year-end 2017 in-service date for the NEXUS Pipeline Not met31 Dec 2017
DTE Energyannounced 26 Apr 2017 Begin operations at the new landfill gas plant No record found30 Jun 2018
DTE Energyannounced 26 Apr 2017 Place the combined heat and power plant in service due after leader left No record found31 Dec 2019
DTE Energyannounced 27 Mar 2017 Complete major investments at 20-25 substations due after leader left No record found31 Dec 2021
DTE Energyannounced 17 Mar 2017 Upgrade circuits to impact 33% of DTE Electric circuits due after leader left No record found31 Dec 2020
DTE Energyannounced 4 Nov 2016 Reach 33% of circuits impacted by the circuit upgrade program due after leader left No record found31 Dec 2020
DTE Energyannounced 4 Nov 2016 Make major investments at 20-25 substations to address load growth due after leader left No record found31 Dec 2021
DTE Energyannounced 26 Sep 2016 Close the acquisition of Appalachia Gathering System and Stonewall Gas Gathering assets Met31 Dec 2016
DTE Energyannounced 13 Sep 2016 Complete a 0.1 Bcf/d lateral expansion of the Millennium Pipeline No record found30 Jun 2017
DTE Energyannounced 6 Jun 2016 Bring the NEXUS pipeline project into service Not met31 Dec 2017
DTE Energyannounced 26 Apr 2016 Complete the automated meter installation project No record found31 Dec 2016
DTE Energyannounced 10 Feb 2016 Submit FERC pre-filing for the Millennium pipeline expansion No record found31 Mar 2016
DTE Energyannounced 10 Feb 2016 Place the Valley Lateral pipeline in service No record found30 Jun 2017
DTE Energyannounced 10 Feb 2016 Place the Millennium pipeline expansion in service No record found31 Dec 2018
DTE Energy Co.announced 7 Jan 2016 Submit initial compliance plans for the Clean Power Plan Condition not met30 Sep 2016
DTE Energy Co.announced 7 Jan 2016 Self-implement DTE Gas rates Met30 Nov 2016
DTE Energy Co.announced 7 Jan 2016 Begin commercial operation of the NEXUS pipeline Not met31 Dec 2017

Is this record wrong, or are you Gerard M. Anderson? Add a statement or ask for a correction.

The Deadline Report

One email a week: the corporate commitments that came due, which were met, which slipped, and what is due next. Free. Stop any time.

No advertising. We never sell or share your address.