Executive Record

Gary Goldberg

Chief executive: Newmont (before 2014 to 4 Feb 2019); Newmont (before 2014 to 14 Jan 2019)

60commitments announced
56with a clear outcome
48met on time
86%on-time rate

Commitments are credited to the chief executive in office on the day they were announced. Where a deadline fell after the leader left, the entry is marked. Sources for each leadership change: Newmont filing, Newmont filing.

Commitments announced under Gary Goldberg

Newmontannounced 14 Jan 2019 Close the acquisition of Goldcorp due after leader left Met30 Jun 2019
Newmontannounced 14 Jan 2019 List the combined entity on the NYSE and TSX due after leader left Met30 Jun 2019
Newmontannounced 6 Dec 2018 Reach a full-funds decision for the second expansion at Tanami due after leader left No record found31 Dec 2019
Newmontannounced 6 Dec 2018 Reach a full-funds decision for the second expansion at Tanami due after leader left No record found31 Dec 2019
Newmontannounced 25 Oct 2018 Lower Tanami power costs due after leader left Met31 Mar 2019
Newmontannounced 25 Oct 2018 Lower Tanami power costs due after leader left Met31 Mar 2019
Newmontannounced 22 Feb 2018 Achieve commercial production at Twin Underground Late30 Jun 2018
Newmontannounced 22 Feb 2018 Achieve commercial production at Subika Underground Met31 Dec 2018
Newmontannounced 22 Feb 2018 Achieve commercial production at Quecher Main due after leader left Met31 Dec 2019
Newmontannounced 22 Feb 2018 Achieve commercial production at Twin Underground Late30 Jun 2018
Newmontannounced 22 Feb 2018 Achieve commercial production at Subika Underground Met31 Dec 2018
Newmontannounced 22 Feb 2018 Achieve commercial production at Quecher Main due after leader left Met31 Dec 2019
Newmontannounced 21 Feb 2018 Recalculate reserves and resources Met31 Dec 2018
Newmontannounced 21 Feb 2018 Recalculate reserves and resources Met31 Dec 2018
Newmontannounced 6 Dec 2017 Reach a decision on the Tanami Power project Met31 Dec 2017
Newmontannounced 6 Dec 2017 Reach a decision on the Tanami Power project Met31 Dec 2017
Newmontannounced 25 Jul 2017 Reach commercial production at the Twin Underground mine Late30 Jun 2018
Newmontannounced 25 Jul 2017 Reach commercial production at the Ahafo Mill Expansion due after leader left Met31 Dec 2019
Newmontannounced 25 Jul 2017 Reach commercial production at the Twin Underground mine Late30 Jun 2018
Newmontannounced 25 Jul 2017 Reach commercial production at the Ahafo Mill Expansion due after leader left Met31 Dec 2019
Newmontannounced 21 Feb 2017 Make a project decision for the Ahafo Mill Expansion project Met30 Jun 2017
Newmontannounced 21 Feb 2017 Make a project decision for the Subika Underground project Met30 Jun 2017
Newmontannounced 21 Feb 2017 Make a project decision for the Quecher Main project Met31 Dec 2017
Newmontannounced 21 Feb 2017 Achieve first production at the Subika Underground project Met31 Dec 2017
Newmontannounced 21 Feb 2017 Begin commercial production at the Subika Underground project Met31 Dec 2018
Newmontannounced 21 Feb 2017 Achieve first production at the Twin Underground project Met31 Dec 2018
Newmontannounced 21 Feb 2017 Achieve first production at the Quecher Main project due after leader left No record found31 Dec 2019
Newmontannounced 21 Feb 2017 Achieve first production at the Ahafo Mill Expansion project due after leader left Met31 Dec 2019
Newmontannounced 21 Feb 2017 Make a project decision for the Ahafo Mill Expansion project Met30 Jun 2017
Newmontannounced 21 Feb 2017 Make a project decision for the Subika Underground project Met30 Jun 2017
Newmontannounced 21 Feb 2017 Make a project decision for the Quecher Main project Met31 Dec 2017
Newmontannounced 21 Feb 2017 Achieve first production at the Subika Underground project Met31 Dec 2017
Newmontannounced 21 Feb 2017 Begin commercial production at the Subika Underground project Met31 Dec 2018
Newmontannounced 21 Feb 2017 Achieve first production at the Twin Underground project Met31 Dec 2018
Newmontannounced 21 Feb 2017 Achieve first production at the Quecher Main project due after leader left No record found31 Dec 2019
Newmontannounced 21 Feb 2017 Achieve first production at the Ahafo Mill Expansion project due after leader left Met31 Dec 2019
Newmontannounced 26 Oct 2016 Begin producing gold at Long Canyon Met30 Nov 2016
Newmontannounced 26 Oct 2016 Begin gold production at Subika Underground Late31 Dec 2018
Newmontannounced 26 Oct 2016 Begin gold production at Ahafo Mill Expansion due after leader left Met31 Dec 2019
Newmontannounced 26 Oct 2016 Begin producing gold at Long Canyon Met30 Nov 2016
Newmontannounced 26 Oct 2016 Begin gold production at Subika Underground Late31 Dec 2018
Newmontannounced 26 Oct 2016 Begin gold production at Ahafo Mill Expansion due after leader left Met31 Dec 2019
Newmontannounced 20 Jul 2016 Reach first gold production at Northwest Exodus Met30 Sep 2016
Newmontannounced 20 Jul 2016 Review Ahafo Mill Expansion and Subika Underground projects Met31 Dec 2016
Newmontannounced 20 Jul 2016 Deliver additional production at Tanami Met31 Dec 2017
Newmontannounced 20 Jul 2016 Reach first gold production at Northwest Exodus Met30 Sep 2016
Newmontannounced 20 Jul 2016 Review Ahafo Mill Expansion and Subika Underground projects Met31 Dec 2016
Newmontannounced 20 Jul 2016 Deliver additional production at Tanami Met31 Dec 2017
Newmontannounced 30 Jun 2016 Close the sale of the interest in PTNNT Late30 Sep 2016
Newmontannounced 30 Jun 2016 Close the sale of the interest in PTNNT Late30 Sep 2016
Newmontannounced 20 Apr 2016 Complete the Cripple Creek & Victor recovery plant Met31 Dec 2016
Newmontannounced 20 Apr 2016 Complete the Cripple Creek & Victor recovery plant Met31 Dec 2016
Newmontannounced 17 Feb 2016 Achieve first production at the Cripple Creek & Victor expansion leach pad Met30 Jun 2016
Newmontannounced 17 Feb 2016 Reach commercial production at the Merian project Met31 Dec 2016
Newmontannounced 17 Feb 2016 Reach commercial production at Long Canyon Phase 1 Met30 Jun 2017
Newmontannounced 17 Feb 2016 Deliver additional production from the Tanami Expansion Project Met31 Dec 2017
Newmontannounced 17 Feb 2016 Achieve first production at the Cripple Creek & Victor expansion leach pad Met30 Jun 2016
Newmontannounced 17 Feb 2016 Reach commercial production at the Merian project Met31 Dec 2016
Newmontannounced 17 Feb 2016 Reach commercial production at Long Canyon Phase 1 Met30 Jun 2017
Newmontannounced 17 Feb 2016 Deliver additional production from the Tanami Expansion Project Met31 Dec 2017

Is this record wrong, or are you Gary Goldberg? Add a statement or ask for a correction.