Commitments announced under Dennis V. Arriola
| Sempraannounced 2 Nov 2016 | Complete the purchase of the Ventika wind facility in Mexico due after leader left | Met31 Dec 2016 |
| Sempraannounced 4 Aug 2016 | Close IEnova's acquisition of PEMEX's 50-percent interest in the joint venture | Met30 Sep 2016 |
| Sempraannounced 4 Aug 2016 | Complete the 100-megawatt Apple Blossom wind project in Michigan due after leader left | Met31 Dec 2017 |