Commence nacelle fabrication for wind turbine generators
Delivered by the deadline
AI-assessed · human review in progress Found and assessed by AI from the cited sources. Shown with its evidence; it is not counted in any Kept Score until confirmed.
- Announced
- 3 Feb 2025
- Due
- 31 Mar 2025
- Delivered
- Q1 2025
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“Nacelles: Fabrication commencing Q1 2025”
What we found
Evidence strength A What the grades mean
By the Q1 2025 earnings call, Dominion reported 36 nacelles already complete or in final testing, consistent with fabrication starting on schedule in Q1 2025.
-
A Dominion Energy CVOW Feb 2025 update slides States nacelle fabrication commencing Q1 2025.
-
B Dominion Energy Newsroom CVOW update Nacelle fabrication to begin later in Q1 2025.
-
D Dominion Energy Q1 2025 earnings call transcript 36 nacelles complete or awaiting final testing, on/ahead of schedule.
Checked 12 Sep 2026.
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Project other
- Indicative materiality
- Low rules
- Action
- Commence
How this entry was checked
- Commitment recordedRecorded from the company's filing.
- First checkAn AI model read the company's later filings and recorded the outcome with a quoted passage.
- Second check: disagreesGemini (Google) re-read the evidence blind and read it as “no_evidence”.
- Tie-breakA stronger model read the evidence and both earlier answers, without knowing which was recorded, and agrees with the second check.
Not yet confirmed. Shown on the record, but it will not count in any score until it is confirmed. How verification works
Are you Dominion Energy, Inc.? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2025-D-000116 · Corrections policy