Complete Ready Wyoming transmission expansion project and place in service
Delivered by the deadline
AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.
- Announced
- 5 Feb 2025
- Due
- 31 Dec 2025
- Delivered
- 29 Dec 2025
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“The project is being constructed in multiple segments and is expected to be completed and in service by year-end 2025.”
What we found
Evidence strength A What the grades mean
Black Hills Corp completed and energized the Ready Wyoming transmission project by late December 2025, meeting its year-end 2025 deadline.
-
A BLACK HILLS CORP /SD/ - Form 8-K - FY2025 (Q3 update) Q3 2025 SEC filing confirms project on track for year-end 2025 completion
-
D $350 Million Transmission Project Links Wyoming, South Dakota Power Grids States project was completed on Dec. 29, 2025
-
D Black Hills Corp. Completes Ready Wyoming 260-mile Electric Transmission Expansion Project Company press release confirms completion, in service on schedule in December 2025
-
D Ready Wyoming: powering the future | Black Hills Energy Company webpage confirms construction completed in late 2025
Checked 14 Sep 2026.
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- In service
- Indicative materiality
- High rules
- Action
- Complete
- Language
- Expected (“expects”, “plans”)
How this entry was checked
- Commitment recordedRecorded from the company's filing.
- First checkAn AI model read the company's later filings and recorded the outcome with a quoted passage.
- Second check: agreesA different AI model, Gemini (Google), re-read the evidence without being told the outcome and reached the same answer.
Confirmed. This outcome counts towards the company's Kept Score. How verification works
Are you Black Hills Corp.? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2025-BKH-000202 · Corrections policy