KeptIndex

Targa Resources

Begin operations at the Legacy II cryogenic natural gas processing plant

Delivered by the deadline

AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.

Announced
24 Feb 2022
Due
30 Jun 2023
  • Deadline
  • Met
  • Late
  • Not met
  • Today

What the company said

“construct a new 275 MMcf/d cryogenic natural gas processing plant in Permian Midland (the “Legacy II plant”), which is expected to begin operations in the second quarter of 2023.”
  • SourceTarga Resources Form 8-K press release, 2022-02-24
  • FilingSEC filing index
  • Deadline as statedin the second quarter of 2023
  • Deadline used30 Jun 2023, the last day of the stated period
  • TypeFacility
  • Permanent referenceKI-C-2022-TRGP-010304
    Cite as https://keptindex.org/c/KI-C-2022-TRGP-010304/ — this address never changes.

What we found

Evidence strength A What the grades mean

Later 10-Q and 10-K filings state the Legacy II plant commenced operations in the first quarter of 2023, before the June 30, 2023 deadline.

  • A
    Targa Resources 10-Q filed 2023-08-03 Regulatory filing · published 3 Aug 2023 · retrieved 15 Oct 2026 · kept permanently by the SEC · fingerprint 8190847baa32
    “The Legacy II plant commenced operations late in the first quarter of 2023.” ✓ confirmed on the page
  • A
    Targa Resources 10-K filed 2024-02-15 Regulatory filing · published 15 Feb 2024 · retrieved 15 Oct 2026 · kept permanently by the SEC · fingerprint 43698501c395
    “The Legacy II plant commenced operations in the first quarter of 2023.” ✓ confirmed on the page

Market reaction: the shares moved +1.0% against the S&P 500 over the three sessions around the disclosure (2 Aug 2023 to 7 Aug 2023). What this measures

Checked 15 Oct 2026.

Commitment lineage

Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.

  • Deadline drift +1370 days
  • 5 versions
  1. Version 1 · original · stated 24 Feb 2022

    Deadline 30 Jun 2023 (“in the second quarter of 2023”) · target 275 MMcf/d · wording expected

  2. Version 2 · stated 3 Nov 2022

    Deadline 31 Mar 2024 (“the first quarter of 2024”) · wording expected

    “the “Wildcat II plant”), which is expected to begin operations in the first quarter of 2024.”

    Source for this version

  3. Version 3 · stated 2 May 2024

    Deadline 31 Dec 2025 (“in the fourth quarter of 2025”) · wording expected

    “The Pembrook II plant is expected to begin operations in the fourth quarter of 2025”

    Source for this version

  4. Version 4 · stated 5 Nov 2025

    Deadline 30 Sep 2027 (“third quarter of 2027”) · wording expected

    “The Yeti plant is expected to begin operations in the third quarter of 2027.”

    Source for this version

  5. Version 5 · stated 5 Nov 2025

    Deadline 31 Mar 2027 (“first quarter of 2027”) · wording expected

    “The Copperhead plant is expected to begin operations in the first quarter of 2027.”

    Source for this version

  6. Version 6 · stated 19 Feb 2026

    Deadline 31 Dec 2027 (“in the fourth quarter of 2027”) · wording expected

    “Yeti II, which is expected to begin operations in the fourth quarter of 2027.”

    Source for this version

Commitment DNA

The structured record of this commitment. Fields the company did not state are left blank rather than guessed.

Event type
Production start
Indicative materiality
High rules
Action
Begin
Deliverable
Legacy II plant
Target
275 MMcf/d
Where
Permian Midland
Language
Expected (“expects”, “plans”)
In the company’s control
High
Specificity
High

How this entry was checked

  1. Commitment recordedThe company's words were matched word for word against the filing.
  2. First checkAn AI model, Claude (Anthropic), read the company's later filings and recorded the outcome with a quoted passage.
  3. Second check: agreesA different AI model, Gemini (Google), re-read the evidence without being told the outcome and reached the same answer.

Confirmed. This outcome counts towards the company's Kept Score. How verification works

Are you Targa Resources? You can publish an official statement next to this entry, free. Add a statement.

Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.

Report an error in this entry Reference: KI-C-2022-TRGP-010304 · Corrections policy