Complete construction of the Toyota trigeneration platform
Delivered after the deadline (221 days after the deadline)
AI-assessed · human review in progress Found and assessed by AI from the cited sources. Shown with its evidence; it is not counted in any Kept Score until confirmed.
- Announced
- 9 Jun 2022
- Due
- 31 Mar 2023
- Delivered
- 7 Nov 2023
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“remaining construction activity anticipated to be completed in late 2022 or early 2023.”
What we found
Evidence strength A What the grades mean
While construction was completed by June 2023, the project did not meet the requirements to be placed in service and begin exporting power until November 7, 2023, missing the early 2023 deadline.
-
A Fuelcell Energy Inc. 10-Q filed 2023-06-08
“We have completed the construction work on this Tri-generation project at the Port of Long Beach for Toyota” ✓ confirmed on the page
-
A Fuelcell Energy Inc. 10-K filed 2023-12-19
“On November 7, 2023, the Toyota project met the requirements to be placed in service under the BioMAT program with Southern California Edison and began exporting power.” ✓ confirmed on the page
Market reaction: the shares moved +7.5% against the S&P 500 over the three sessions around the disclosure (7 Jun 2023 to 12 Jun 2023). What this measures
Checked 1 Oct 2026.
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Construction
- Indicative materiality
- Medium rules
- Action
- Complete
- Deliverable
- Toyota trigeneration platform construction
- Where
- Long Beach, CA
- Language
- Expected (“expects”, “plans”)
- In the company’s control
- High
- Specificity
- Medium
How this entry was checked
- Commitment recordedThe company's words were matched word for word against the filing.
- First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
- Second check: disagreesClaude (Anthropic) re-read the evidence blind and read it as “no_evidence”.
- Tie-breakA stronger model read the evidence and both earlier answers, without knowing which was recorded, and agrees with the second check.
Not yet confirmed. Shown on the record, but it will not count in any score until it is confirmed. How verification works
Are you Fuelcell Energy Inc.? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2022-FCEL-002377 · Corrections policy