Valero Energy

Complete the Diamond Green Diesel project at Port Arthur (DGD 3)

Delivered by the deadline

AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.

Announced
29 Jul 2021
Due
30 Jun 2023
  • Deadline
  • Met
  • Late
  • Not met
  • Today

What the company said

“Advanced the expected completion of the Diamond Green Diesel project at Port Arthur (DGD 3) to the first half of 2023”

What we found

Evidence strength A What the grades mean

Later 10-K and 10-Q filings state the DGD Port Arthur plant was completed and began operations in Q4 2022, before the first-half 2023 deadline.

  • A
    Valero Energy 8-K filed 2023-07-27 Regulatory filing · published 27 Jul 2023 · retrieved 15 Oct 2026 · kept permanently by the SEC · fingerprint c7165f80706e
    “the startup of the DGD Port Arthur plant in the fourth quarter of 2022” ✓ confirmed on the page
  • A
    Valero Energy 10-Q filed 2023-10-26 Regulatory filing · published 26 Oct 2023 · retrieved 15 Oct 2026 · kept permanently by the SEC · fingerprint 819de41a98d2
    “the completion of the new DGD Port Arthur Plant that commenced operations in the fourth quarter of 2022” ✓ confirmed on the page
  • A
    Valero Energy 10-K filed 2024-02-22 Regulatory filing · published 22 Feb 2024 · retrieved 15 Oct 2026 · kept permanently by the SEC · fingerprint 9a4b888b32be
    “in the fourth quarter of 2022, we completed construction of DGD’s second renewable diesel plant” ✓ confirmed on the page

Market reaction: the shares moved +1.7% against the S&P 500 over the three sessions around the disclosure (26 Jul 2023 to 31 Jul 2023). What this measures

Checked 15 Oct 2026.

Commitment lineage

Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.

  • Deadline drift +550 days
  • 4 versions
  1. Version 1 · original · stated 29 Jul 2021

    Deadline 30 Jun 2023 (“first half of 2023”) · wording expected

  2. Version 2 · stated 27 Jan 2022

    Deadline 31 Mar 2023 (“first quarter of 2023”) · wording expected

    “The DGD project at Valero’s Port Arthur refinery (DGD 3)... is now expected to commence operations in the first quarter of 2023”

    Source for this version

  3. Version 3 · stated 26 Apr 2022

    Deadline 31 Dec 2022 (“the fourth quarter of 2022”) · wording expected

    “Accelerated the expected completion of the Diamond Green Diesel project at Port Arthur (DGD 3) to the fourth quarter of 2022”

    Source for this version

  4. Version 4 · stated 1 May 2024

    Deadline 31 Dec 2024 (“fourth quarter of 2024”) · wording expected

    “DGD Port Arthur SAF Project • Large-scale SAF project at the recently constructed DGD Port Arthur plant is expected to be completed in the fourth quarter of 2024”

    Source for this version

Commitment DNA

The structured record of this commitment. Fields the company did not state are left blank rather than guessed.

Event type
Construction
Indicative materiality
Medium rules
Action
Complete
Deliverable
Diamond Green Diesel project at Port Arthur (DGD 3)
Where
Port Arthur
Language
Expected (“expects”, “plans”)
In the company’s control
High
Specificity
High

How this entry was checked

  1. Commitment recordedThe company's words were matched word for word against the filing.
  2. First checkAn AI model, Claude (Anthropic), read the company's later filings and recorded the outcome with a quoted passage.
  3. Second check: agreesA different AI model, Gemini (Google), re-read the evidence without being told the outcome and reached the same answer.

Confirmed. This outcome counts towards the company's Kept Score. How verification works

Are you Valero Energy? You can publish an official statement next to this entry, free. Add a statement.

Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.

Report an error in this entry Reference: KI-C-2021-VLO-010509 · Corrections policy