Begin commissioning of the Nicaragua power plant
Not delivered by the deadline
AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.
- Announced
- 3 Nov 2021
- Due
- 31 Mar 2022
- Checked
- 2 Oct 2026
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“we expect to begin commissioning of our power plant in Q1 2022”
What we found
Evidence strength B What the grades mean
Commissioning did not begin in Q1 2022; as of November 2022 the project remained under construction with multiple subsequent delays into 2026.
-
B New Fortress Energy Announces Third Quarter 2021 Results
“we are completing terminal and power plant construction in Q4 2021, and we expect to begin commissioning of our power plant in Q1 2022.”
-
D Puerto Sandino FSRU - Global Energy Monitor
“in August 2024 the company's Q2 2024 results report noted that the Puerto Sandino terminal was 90% complete and expected to begin service in the fourth quarter of 2024.” ✓ confirmed on the page
-
D Puerto Sandino LNG power plant - Global Energy Monitor
“as of November 2022, New Fortress Energy's most recent filings with the US Securities and Exchange Commission indicated that the project was still under construction” ✓ confirmed on the page
-
D New Fortress Energy Near Bankruptcy, Bets on Nicaragua Gas Plant Launch in October 2026
“We expect the terminal to begin operations in October 2026 following this transaction” ✓ confirmed on the page
Checked 2 Oct 2026.
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Facility opening
- Indicative materiality
- High rules
- Action
- Begin
- Deliverable
- Nicaragua power plant
- Where
- Nicaragua
- Language
- Expected (“expects”, “plans”)
- In the company’s control
- High
- Specificity
- High
How this entry was checked
- Commitment recordedThe company's words were matched word for word against the filing.
- First checkAn AI model, Claude (Anthropic), read the company's later filings and recorded the outcome with a quoted passage.
- Second check: agreesA different AI model, Gemini (Google), re-read the evidence without being told the outcome and reached the same answer.
- Third check on a negative finding: agreesBecause a negative finding could harm a company if wrong, a stronger model re-read the evidence fully blind and reached the same answer.
Confirmed. This outcome counts towards the company's Kept Score. How verification works
Are you New Fortress Energy Inc.? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2021-NFE-003842 · Corrections policy