Newmont

Achieve commercial production at the Tanami Expansion 2 project

Not delivered by the deadline

AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.

Announced
29 Apr 2021
Due
30 Jun 2024
Checked
19 Oct 2026
  • Deadline
  • Met
  • Late
  • Not met
  • Today

What the company said

“Capital costs for the project are estimated to be between $850 million and $950 million with a commercial production date in the first half of 2024.”
  • SourceNewmont Form 8-K press release, 2021-04-29
  • FilingSEC filing index
  • Deadline as statedin the first half of 2024
  • Deadline used30 Jun 2024, the last day of the stated period
  • TypeProject
  • Permanent referenceKI-C-2021-NEM-015217
    Cite as https://keptindex.org/c/KI-C-2021-NEM-015217/ — this address never changes.

What we found

Evidence strength A What the grades mean

Newmont's filings confirm that the Tanami Expansion 2 project did not achieve commercial production by the first half of 2024, with the expected date revised to the second half of 2027.

  • A
    Newmont 10-K filed 2025-02-21 Regulatory filing · published 21 Feb 2025 · retrieved 19 Oct 2026 · kept permanently by the SEC · fingerprint 50d47da25011
    “Capital costs are estimated to be between $1,700 and $1,800 for Tanami Expansion 2 with an expected commercial production date in the second half of 2027.” ✓ confirmed on the page

Market reaction: the shares moved -8.1% against the S&P 500 over the three sessions around the disclosure (20 Feb 2025 to 25 Feb 2025). What this measures

Checked 19 Oct 2026.

Commitment lineage

Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.

  • Deadline drift +184 days
  • 3 versions
  1. Version 1 · original · stated 29 Apr 2021

    Deadline 30 Jun 2024 (“in the first half of 2024”)

  2. Version 2 · stated 28 Oct 2021

    Deadline 31 Mar 2024 (“early 2024”)

    “commercial production in early 2024”

    Source for this version

  3. Version 3 · stated 22 Apr 2022

    Deadline 31 Dec 2024 (“2024”)

    “Capital costs for the project are estimated to be between $850 and $950 million with a commercial production date in 2024.”

    Source for this version

Commitment DNA

The structured record of this commitment. Fields the company did not state are left blank rather than guessed.

Event type
Project other
Indicative materiality
Low rules
Action
Achieve
Deliverable
Tanami Expansion 2 commercial production
Where
Australia
In the company’s control
High
Specificity
High

How this entry was checked

  1. Commitment recordedThe company's words were matched word for word against the filing.
  2. First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
  3. Second check: agreesA different AI model, Claude (Anthropic), re-read the evidence without being told the outcome and reached the same answer.
  4. Third check on a negative finding: agreesBecause a negative finding could harm a company if wrong, a stronger model re-read the evidence fully blind and reached the same answer.

Confirmed. This outcome counts towards the company's Kept Score. How verification works

Are you Newmont? You can publish an official statement next to this entry, free. Add a statement.

Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.

Report an error in this entry Reference: KI-C-2021-NEM-015217 · Corrections policy

The Deadline Report

One email a week: the corporate commitments that came due, which were met, which slipped, and what is due next. Free. Stop any time.

No advertising. We never sell or share your address.