Achieve substantial completion of Train 3 of the CCL Project
Delivered by the deadline
AI-assessed · human review in progress Found and assessed by AI from the cited sources. Shown with its evidence; it is not counted in any Kept Score until confirmed.
- Announced
- 24 Feb 2021
- Due
- 31 Mar 2021
- Delivered
- 26 Mar 2021
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“the project remains on track to achieve substantial completion in first quarter 2021”
What we found
Evidence strength A What the grades mean
A May 2021 10-Q states that the third Train of the CCL Project achieved substantial completion on March 26, 2021, before the March 31, 2021 deadline.
-
A Cheniere Energy, Inc. 10-Q filed 2021-05-04
“including the third Train which achieved substantial completion on March 26, 2021, for a total production capacity of approximately 15 mtpa of LNG” ✓ confirmed on the page
-
A Cheniere Energy, Inc. 10-Q filed 2021-05-04
“including the third Train which achieved substantial completion on March 26, 2021, with a total production capacity of approximately 15 mtpa of LNG” ✓ confirmed on the page
Checked 26 Oct 2026.
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Project other
- Indicative materiality
- Low rules
- Action
- Achieve
- Deliverable
- Train 3 of the CCL Project substantial completion
- Where
- Corpus Christi, Texas
- Language
- Firm (“will”, “on track to”)
- In the company’s control
- Medium
- Specificity
- High
How this entry was checked
- Commitment recordedThe company's words were matched word for word against the filing.
- First checkAn AI model, Claude (Anthropic), read the company's later filings and recorded the outcome with a quoted passage.
Not yet confirmed. Shown on the record, but it will not count in any score until it is confirmed. How verification works
Are you Cheniere Energy, Inc.? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2021-LNG-024272 · Corrections policy