Kinder Morgan, Inc.

Place the Bradshaw Terminal renewable diesel rail hub in service

Delivered after the deadline (3 days after the deadline)

AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.

Announced
20 Oct 2021
Due
31 Mar 2023
Delivered
3 Apr 2023
  • Deadline
  • Met
  • Late
  • Not met
  • Today

What the company said

“anticipates that it will be in service in the first quarter of 2023.”
  • SourceKinder Morgan Form 8-K press release, 2021-10-20
  • FilingSEC filing index
  • Deadline as statedthe first quarter of 2023
  • Deadline used31 Mar 2023, the last day of the stated period
  • TypeFacility
  • Permanent referenceKI-C-2021-KMI-009459
    Cite as https://keptindex.org/c/KI-C-2021-KMI-009459/ — this address never changes.

What we found

Evidence strength A What the grades mean

The company placed its renewable diesel hubs in California into commercial operation on April 3, 2023, which was shortly after the first quarter 2023 deadline.

  • A
    Kinder Morgan 8-K filed 2023-04-19 Regulatory filing · published 19 Apr 2023 · retrieved 15 Oct 2026 · kept permanently by the SEC · fingerprint 7c8977df5d67
    “KMI’s Southern and Northern California RD hubs were placed in commercial operation on April 3, 2023.” ✓ confirmed on the page

Market reaction: the shares moved -1.4% against the S&P 500 over the three sessions around the disclosure (18 Apr 2023 to 21 Apr 2023). What this measures

Checked 15 Oct 2026.

Commitment lineage

Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.

  • 2 versions
  1. Version 1 · original · stated 20 Oct 2021

    Deadline 31 Mar 2023 (“the first quarter of 2023”) · wording expected

  2. Version 2 · stated 19 Jan 2022

    Deadline 31 Dec 2022 (“in December 2022”) · wording expected

    “This project is currently expected to be in service in December 2022.”

    Source for this version

  3. Version 3 · stated 20 Apr 2022

    Deadline 31 Mar 2023 (“the first quarter of 2023”) · target 15,000 barrels per day

    “We are constructing a $36 million renewable diesel rail hub to accommodate up to 15,000 barrels per day of blended diesel throughput at the truck rack. This project is supported by customer commitments and is”

    Source for this version

Commitment DNA

The structured record of this commitment. Fields the company did not state are left blank rather than guessed.

Event type
In service
Indicative materiality
High rules
Action
Place
Deliverable
Bradshaw Terminal renewable diesel rail hub
Where
California
Language
Expected (“expects”, “plans”)
In the company’s control
High
Specificity
High

How this entry was checked

  1. Commitment recordedThe company's words were matched word for word against the filing.
  2. First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
  3. Second check: disagreesClaude (Anthropic) re-read the evidence blind and read it as “no_evidence”.
  4. Tie-breakA stronger model read the evidence and both earlier answers, without knowing which was recorded, and agrees with the recorded outcome.

Confirmed. This outcome counts towards the company's Kept Score. How verification works

Are you Kinder Morgan? You can publish an official statement next to this entry, free. Add a statement.

Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.

Report an error in this entry Reference: KI-C-2021-KMI-009459 · Corrections policy