Kinder Morgan, Inc.

Place the remaining six liquefaction units into service

Delivered after the deadline

AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.

Announced
22 Jan 2020
Due
30 Jun 2020
Delivered
August 2020
  • Deadline
  • Met
  • Late
  • Not met
  • Today

What the company said

“The remaining six units are scheduled to be placed in service during the first half of 2020.”

What we found

Evidence strength A What the grades mean

The company failed to place all six remaining liquefaction units into service by the first half of 2020, as the final units were not completed until August 2020.

  • A
    Kinder Morgan 8-K filed 2020-07-22 Regulatory filing · published 22 Jul 2020 · retrieved 13 Oct 2026 · kept permanently by the SEC · fingerprint 650e52a692f2
    “The remaining three units are expected to be placed in service before the end of this summer.” ✓ confirmed on the page
  • A
    Kinder Morgan 10-K filed 2021-02-05 Regulatory filing · published 5 Feb 2021 · retrieved 13 Oct 2026 · kept permanently by the SEC · fingerprint dd6db2da561f
    “The remaining seven units were placed in service during January through August 2020.” ✓ confirmed on the page

Market reaction: the shares moved -4.3% against the S&P 500 over the three sessions around the disclosure (21 Jul 2020 to 24 Jul 2020). What this measures

Checked 13 Oct 2026.

Commitment lineage

Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.

  • Deadline drift +84 days
  • Language weakened: firm → expected
  • 3 versions
  1. Version 1 · original · stated 22 Jan 2020

    Deadline 30 Jun 2020 (“first half of 2020”) · wording firm

  2. Version 2 · stated 22 Apr 2020

    Deadline 30 Sep 2020 (“during the spring and summer of this year”) · wording expected

    “The remaining four units are expected to be placed in service during the spring and summer of this year”

    Source for this version

  3. Version 3 · stated 22 Jul 2020

    Deadline 22 Sep 2020 (“before the end of this summer”) · wording expected

    “The remaining three units are expected to be placed in service before the end of this summer.”

    Source for this version

Commitment DNA

The structured record of this commitment. Fields the company did not state are left blank rather than guessed.

Event type
In service
Indicative materiality
High rules
Action
Place
Deliverable
six liquefaction units
Language
Firm (“will”, “on track to”)
In the company’s control
High
Specificity
High

How this entry was checked

  1. Commitment recordedThe company's words were matched word for word against the filing.
  2. First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
  3. Second check: disagreesClaude (Anthropic) re-read the evidence blind and read it as “Partly met”.
  4. Tie-breakA stronger model read the evidence and both earlier answers, without knowing which was recorded, and agrees with the recorded outcome.

Confirmed. This outcome counts towards the company's Kept Score. How verification works

Are you Kinder Morgan? You can publish an official statement next to this entry, free. Add a statement.

Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.

Report an error in this entry Reference: KI-C-2020-KMI-009430 · Corrections policy

The Deadline Report

One email a week: the corporate commitments that came due, which were met, which slipped, and what is due next. Free. Stop any time.

No advertising. We never sell or share your address.