Reach full production capacity at the Liza Destiny FPSO
Delivered after the deadline
AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.
- Announced
- 7 May 2020
- Due
- 30 Jun 2020
- Delivered
- December 2020
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“the Liza Destiny floating production, offloading, and storage vessel (FPSO) is expected to reach its full capacity of 120,000 gross barrels of oil per day (bopd) in June”
What we found
Evidence strength A What the grades mean
The company did not reach the 120,000 gross bopd capacity by the June 2020 deadline, achieving this milestone in December 2020 instead.
-
A Hess Corporation 10-Q filed 2020-08-06
“should enable the Liza Destiny floating production, offloading and storage vessel (FPSO) to reach its capacity of 120,000 gross bopd in August.” ✓ confirmed on the page
-
A Hess Corporation 10-K filed 2021-03-01
“During the fourth quarter, the operator Esso Exploration and Production Guyana Limited, reached its nameplate capacity of 120,000 gross bopd.” ✓ confirmed on the page
-
A Hess Corporation 10-K filed 2021-03-01
“The Liza Phase 1 development, which was sanctioned in 2017, began producing oil in December 2019 from the Liza Destiny FPSO and reached its nameplate production capacity of 120,000 gross bopd in December 2020.” ✓ confirmed on the page
Checked 20 Oct 2026.
Commitment lineage
Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.
- Deadline drift +822 days
- Scope drift +83.3%
- 4 versions
-
Version 1 · original · stated 7 May 2020
Deadline 30 Jun 2020 (“in June”) · target 120,000 bopd · wording expected
-
Version 2 · stated 29 Jul 2020
Deadline 31 Aug 2020 (“in August”) · target 120,000 gross bopd
“enable the Liza Destiny floating production, offloading, and storage vessel (FPSO) to reach its capacity of 120,000 gross bopd in August.”
-
Version 3 · stated 28 Oct 2020
Deadline 31 Dec 2020 (“in the fourth quarter”) · target 120,000 bopd
“enable the Liza Destiny floating production, storage and offloading vessel (FPSO) to reach its capacity of 120,000 gross bopd in the fourth quarter”
-
Version 4 · stated 27 Apr 2022
Deadline 30 Sep 2022 (“by the third quarter”) · target 220,000 bopd · wording expected
“The Liza Unity FPSO is expected to reach its production capacity of approximately 220,000 gross bopd by the third quarter.”
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Capacity change
- Indicative materiality
- Medium rules
- Action
- Reach
- Deliverable
- Liza Destiny FPSO production capacity
- Target
- 120,000 bopd
- Where
- Guyana
- Language
- Expected (“expects”, “plans”)
- In the company’s control
- High
- Specificity
- High
How this entry was checked
- Commitment recordedThe company's words were matched word for word against the filing.
- First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
- Second check: agreesA different AI model, Claude (Anthropic), re-read the evidence without being told the outcome and reached the same answer.
Confirmed. This outcome counts towards the company's Kept Score. How verification works
Are you Hess Corporation? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2020-C004447-017561 · Corrections policy