Make the new plate mill fully operational
Delivered by the deadline
AI-assessed · human review in progress Found and assessed by AI from the cited sources. Shown with its evidence; it is not counted in any Kept Score until confirmed.
- Announced
- 7 Jan 2019
- Due
- 31 Dec 2022
- Delivered
- December 2022
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“fully operational in 2022”
What we found
Evidence strength A What the grades mean
Nucor completed construction of its new plate mill in Brandenburg, Kentucky, and successfully rolled its first plate in December 2022, meeting the commitment to be operational within 2022.
-
A Nucor 10-K filed 2023-03-01
“Nucor completed construction on a state-of-the-art plate mill in Brandenburg, Kentucky that rolled its first plate in December 2022.” ✓ confirmed on the page
-
A Nucor 10-K filed 2023-03-01
“The new plate mill rolled its first plate in December 2022 and we expect to complete final commissioning and begin shipping tons to customers in the first quarter of 2023.” ✓ confirmed on the page
Market reaction: the shares moved +4.5% against the S&P 500 over the three sessions around the disclosure (28 Feb 2023 to 3 Mar 2023). What this measures
Checked 19 Oct 2026.
Commitment lineage
Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.
- 2 versions
-
Version 1 · original · stated 7 Jan 2019
Deadline 31 Dec 2022 (“in 2022”)
-
Version 2 · stated 23 Apr 2019
Deadline 31 Dec 2022 (“in 2022”) · wording expected
“The new plate mill will complement Nucor's existing plate mills in North Carolina, Alabama and Texas and is expected to be fully operational in 2022.”
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Facility other
- Indicative materiality
- Medium rules
- Action
- Make
- Deliverable
- New plate mill
- In the company’s control
- High
- Specificity
- High
How this entry was checked
- Commitment recordedThe company's words were matched word for word against the filing.
- First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
- Second check: disagreesClaude (Anthropic) re-read the evidence blind and read it as “Not met”.
- Tie-breakA stronger model read the evidence and both earlier answers, without knowing which was recorded, and agrees with the second check.
Not yet confirmed. Shown on the record, but it will not count in any score until it is confirmed. How verification works
Are you Nucor? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2019-NUE-015285 · Corrections policy