Nucor

Commission the new plate mill

Delivered after the deadline

AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.

Announced
7 Jan 2019
Due
31 Dec 2022
Delivered
Q1 2023
  • Deadline
  • Met
  • Late
  • Not met
  • Today

What the company said

“the mill, which is expected to be fully operational in 2022 and will be capable of producing 1.2 million tons per year of steel plate products”
  • SourceNucor Form 8-K press release, 2019-01-07
  • FilingSEC filing index
  • Deadline as statedin 2022
  • Deadline used31 Dec 2022, the last day of the stated period
  • TypeFacility
  • Permanent referenceKI-C-2019-NUE-015283
    Cite as https://keptindex.org/c/KI-C-2019-NUE-015283/ — this address never changes.

What we found

Evidence strength A What the grades mean

Nucor rolled the first plate in December 2022, but final commissioning and shipping to customers were not completed until the first quarter of 2023, missing the 2022 operational deadline.

  • A
    Nucor 10-K filed 2024-02-27 Regulatory filing · published 27 Feb 2024 · retrieved 19 Oct 2026 · kept permanently by the SEC · fingerprint 301db280b7ba
    “The new plate mill rolled its first plate in December 2022 and completed final commissioning and began shipping tons to customers in the first quarter of 2023.” ✓ confirmed on the page
  • A
    Nucor 10-K filed 2023-03-01 Regulatory filing · published 1 Mar 2023 · retrieved 19 Oct 2026 · kept permanently by the SEC · fingerprint 0a4103c4b84e
    “The new plate mill rolled its first plate in December 2022 and we expect to complete final commissioning and begin shipping tons to customers in the first quarter of 2023.” ✓ confirmed on the page

Market reaction: the shares moved +4.5% against the S&P 500 over the three sessions around the disclosure (28 Feb 2023 to 3 Mar 2023). What this measures

Checked 19 Oct 2026.

Commitment DNA

The structured record of this commitment. Fields the company did not state are left blank rather than guessed.

Event type
Facility other
Indicative materiality
Medium rules
Action
Commission
Deliverable
plate mill
Target
1.2 million tons per year
Where
U.S. Midwest
Language
Expected (“expects”, “plans”)
In the company’s control
High
Specificity
High

How this entry was checked

  1. Commitment recordedThe company's words were matched word for word against the filing.
  2. First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
  3. Second check: agreesA different AI model, Claude (Anthropic), re-read the evidence without being told the outcome and reached the same answer.

Confirmed. This outcome counts towards the company's Kept Score. How verification works

Are you Nucor? You can publish an official statement next to this entry, free. Add a statement.

Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.

Report an error in this entry Reference: KI-C-2019-NUE-015283 · Corrections policy