Commission the South Fork Wind Farm

Not delivered by the deadline

AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.

Announced
8 Feb 2019
Due
31 Dec 2022
Checked
16 Oct 2026
  • Deadline
  • Met
  • Late
  • Not met
  • Today

What the company said

“Subject to permitting, further development, and final investment decisions by Ørsted and Eversource, South Fork is expected to be commissioned by the end of 2022.”

What we found

Evidence strength A What the grades mean

The 2023 filings describe South Fork Wind as still under construction, and the February 2024 10-K expects full service only by end of March 2024, after the 2022 deadline.

  • A
    Eversource Energy 10-K filed 2023-02-15 Regulatory filing · published 15 Feb 2023 · retrieved 16 Oct 2026 · kept permanently by the SEC · fingerprint 7e6793a32bc0
    “Construction of South Fork Wind is underway.” ✓ confirmed on the page
  • A
    Eversource Energy 10-K filed 2024-02-14 Regulatory filing · published 14 Feb 2024 · retrieved 16 Oct 2026 · kept permanently by the SEC · fingerprint 6a4a6c5804b2
    “All of South Fork Wind’s twelve turbines are expected to be installed and placed into service by the end of March 2024.” ✓ confirmed on the page

Market reaction: the shares moved +3.0% against the S&P 500 over the three sessions around the disclosure (14 Feb 2023 to 17 Feb 2023). What this measures

Checked 16 Oct 2026.

Commitment DNA

The structured record of this commitment. Fields the company did not state are left blank rather than guessed.

Event type
Project other
Indicative materiality
Low rules
Action
Commission
Deliverable
South Fork Wind Farm
Where
Long Island, New York
Language
Expected (“expects”, “plans”)
In the company’s control
Low
Specificity
Medium
Conditional
Yes: subject to permitting; subject to further development; subject to final investment decisions by Ørsted and Eversource
Depends on
Regulatory, Counterparty, Partner

How this entry was checked

  1. Commitment recordedThe company's words were matched word for word against the filing.
  2. First checkAn AI model, Claude (Anthropic), read the company's later filings and recorded the outcome with a quoted passage.
  3. Second check: agreesA different AI model, Gemini (Google), re-read the evidence without being told the outcome and reached the same answer.
  4. Third check on a negative finding: agreesBecause a negative finding could harm a company if wrong, a stronger model re-read the evidence fully blind and reached the same answer.

Confirmed. This outcome counts towards the company's Kept Score. How verification works

Are you Eversource Energy? You can publish an official statement next to this entry, free. Add a statement.

Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.

Report an error in this entry Reference: KI-C-2019-ES-011222 · Corrections policy

The Deadline Report

One email a week: the corporate commitments that came due, which were met, which slipped, and what is due next. Free. Stop any time.

No advertising. We never sell or share your address.