Expand acetic acid production capacity at the Clear Lake facility
Not delivered by the deadline
AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.
- Announced
- 28 Jan 2019
- Due
- 31 Dec 2021
- Checked
- 20 Oct 2026
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“expanding Clear Lake, Texas acetic acid capacity to approximately 2.0 million tons by late 2021”
What we found
Evidence strength A What the grades mean
The company reported in February 2022 that the acetic acid expansion project in Clear Lake, Texas was still in construction, indicating it was not completed by the late 2021 deadline.
-
A Celanese 8-K filed 2022-01-27
“Capital expenditures in the year were $467 million as the Company progressed on several key projects including the 1.3 million ton acetic acid expansion in Clear Lake, Texas.” ✓ confirmed on the page
-
A Celanese 10-K filed 2022-02-10
“our previously announced acetic acid expansion in Clear Lake, Texas is still in construction and on schedule.” ✓ confirmed on the page
Market reaction: the shares moved +0.0% against the S&P 500 over the three sessions around the disclosure (9 Feb 2022 to 14 Feb 2022). What this measures
Checked 20 Oct 2026.
Commitment lineage
Every time the company restated this commitment. The original is never changed, and the outcome is always measured against version 1.
- Deadline drift +455 days
- 2 versions
-
Version 1 · original · stated 28 Jan 2019
Deadline 31 Dec 2021 (“by late 2021”) · target 2 million tons
-
Version 2 · stated 21 Oct 2021
Deadline 31 Mar 2023 (“in early 2023”)
“With the completion of the acetic acid expansion at Clear Lake in early 2023”
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Capacity change
- Indicative materiality
- Medium rules
- Action
- Expand
- Deliverable
- Clear Lake acetic acid capacity
- Target
- 2 million tons
- Where
- Clear Lake, Texas
- In the company’s control
- High
- Specificity
- High
How this entry was checked
- Commitment recordedThe company's words were matched word for word against the filing.
- First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
- Second check: agreesA different AI model, Claude (Anthropic), re-read the evidence without being told the outcome and reached the same answer.
- Third check on a negative finding: agreesBecause a negative finding could harm a company if wrong, a stronger model re-read the evidence fully blind and reached the same answer.
Confirmed. This outcome counts towards the company's Kept Score. How verification works
Are you Celanese? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2019-CE-017355 · Corrections policy