Take delivery of the first drillship from Jurong Shipyard
Not delivered by the deadline
AI-confirmed · human review in progress Independent AI checks agreed on primary SEC or regulator evidence. Records are now being reviewed by hand, starting with those our customers order.
- Announced
- 24 Apr 2017
- Due
- 31 Mar 2020
- Checked
- 24 Oct 2026
- Deadline
- Met
- Late
- Not met
- Today
What the company said
“The two drillships on order from Sembcorp Marine's subsidiary, Jurong Shipyard, are expected to be delivered in the first quarter and third quarter of 2020.”
What we found
Evidence strength A What the grades mean
The company did not take delivery of the first drillship by the first quarter of 2020; subsequent filings indicate the delivery date was pushed to the fourth quarter of 2020 and later.
-
A Transocean 10-Q filed 2020-04-30
“Deepwater Atlas, an ultra-deepwater drillship under construction at the Jurong Shipyard Pte Ltd. in Singapore does not yet have a drilling contract and is contracted to be delivered in the fourth quarter of 2020.” ✓ confirmed on the page
Market reaction: the shares moved +13.1% against the S&P 500 over the three sessions around the disclosure (29 Apr 2020 to 4 May 2020). What this measures
Checked 24 Oct 2026.
Commitment DNA
The structured record of this commitment. Fields the company did not state are left blank rather than guessed.
- Event type
- Delivery
- Indicative materiality
- Medium rules
- Action
- Take
- Deliverable
- Drillship
- Language
- Expected (“expects”, “plans”)
- In the company’s control
- Medium
- Specificity
- High
- Depends on
- Supplier
How this entry was checked
- Commitment recordedThe company's words were matched word for word against the filing.
- First checkAn AI model, Gemini (Google), read the company's later filings and recorded the outcome with a quoted passage.
- Second check: agreesA different AI model, Claude (Anthropic), re-read the evidence without being told the outcome and reached the same answer.
- Third check on a negative finding: agreesBecause a negative finding could harm a company if wrong, a stronger model re-read the evidence fully blind and reached the same answer.
Confirmed. This outcome counts towards the company's Kept Score. How verification works
Are you Transocean? You can publish an official statement next to this entry, free. Add a statement.
Is something here wrong or out of date? Companies and readers can ask us to check it. Please bring a link to a public source.
Report an error in this entry Reference: KI-C-2017-RIG-020771 · Corrections policy